Power shutdown in areas of Jammu & Kathua


Cinosural International An Elementry School Jammu

 

JAMMU, Dec 24: In order to carry out the work of insertion of 16 meter long ST poles to raise the height of conductor of 66 KV tower line between Saharkhad to Barnoti, the power supply to Logate Industrial area, Sakta-Chak Industrial area, Palli, Nagri, Barnoti, Jarmal, Jakhbar, Saidpur, Barwal, Budhi, Nanan, Bhakta and its adjoining areas shall remain affected on December 26, 2015from 9 a m to 5 p m.

Similarly in order to carry out the work of insertion of 13 meter long ST pole to raise the height of conductor of 66 KV Hatli village feeder emanating from 132/66 KV, 120 MVA Grid Station Kathua, the power supply to Hatli village, Maroli, Oat, Mangot, Dukth, IID and their adjoining areas shall remain affected onDecember 27, 2015 from 9 a m to 5 p m.

In  order to carry out the development works by M/s IRCON under R-APDRP works, 11 KV Feeder CH-3 emanating from 33/11 KVA R/Stn Channi Himmat shall remain under shut down on December 26, 2015 from 9 am to 1 pm.

During the power shut down, the power supply to Channi Himmat Sector 1-A, Sector-3, Bhalla Colony, Police Line Complex and its adjoining areas shall remain affected.

Meanwhile, In order to carry out the development works by M/s IRCON under R-APDRP works, the power supply to Gangyal Industry and its adjoining areas shall remain affected on December 27, 2015 from 8 am to 5 pm.

          Similarly to carry out the development works by M/s IRCON under R-APDRP works, 11 KV feeder RC-1 emanating from 33/11 KVA R/stn Railway Complex, the power supply to Green Belt A/D Block, A/C Block, B/C Block and its adjoining areas shall remain affected on December 26, 2015 from 9 a m to 1 p m.

          Meanwhile in order to carry out the development works by M/s IRCOP under R-APDRP works, 11 KV feeder GK-1, GK-2, GK-3 and GK-4 emanating from 33/11 KVA R/stn Greater Kailash, the power supply to Greater Kailash, Kalu Chack, Ratnu Chack, Parmandal Morh, Jallo Chack and its adjoining areas shall remain affected on December 26, 2015 from 10 a m to 3 p m.

In order to carry out the development works by M/s IRCON International ltd under R-APDRP part-B, 33 KV G-4, G-5 and G-8 (Boria) and 11 KV BFS line emanating from 220/132/33 KV Grid Station Gladni, the power supply to part of Gujjar Nagar, Khatikan Talab, Shahidi Chowk, part of Raghunath Bazar, Gurudwara Sunder Singh Road, Dak Bungalow, Hans Raj park, part of Kanak Mandi, Lakhadata Bazar, Rajender Bazar, PHE Gujjar Nagar, PHE Boria Pumping Station, Panjithriti, Dhounthly, Old Sectt, Pacci Dhakki, Julaka Mohalla, Kachi Chawani, Tangewali Gali, Karan Nagar, Amphalla, Mohalla Ustad, Gujjar Nagar, Pir Mitha, Jain Bazar, Circular Road and adjoining areas shall remain affected onDecember 27, 2015 from 10 a m to 4 p m.

Further, the shutdown of 33 KV G-5 feeder which stands already approved on December 26, 2015 for carrying out works by M/s IRCON shall now be availed on December 27, 2015.

          Similarly to carry out the development works by M/s IRCON International ltd under R-APDRP part-B, 33 KV G-4 line emanating from 220/132/33 KV Grid Station Gladni, the power supply to Prem Nagar, Lower Prem Nagar, Quasim Nagar, Christan Colony, part of Raghunath Bazar, Gujjar Nagar, Bawe Balli Galli, Residency Roads, Denis Gate, Talab Khatika, Jogi Gate and adjoining areas shall remain affected on December 27, 29 and 31, 2015 and January 2, 4 and 6, 2016 from10 a m to 4 p m.

          Meanwhile in order to carry out rectification of hot spots and preventive maintenance by way of tightening and repair/replacement of worn out jumpers, droppers and clamps etc of 220 Kv and 132 KV bays alongwith plugging of oil leakage from “R” phase 220 KV CT of 200 MVA transformer bank way, the shutdown of 320 MVA, 220/132/66 KV Grid Station Hiranagar including 220 KV Hiranagar-Gladni and Sana-Hiranagar transmission lines alongwith 132 KV Hiranagar-Sewa-II D/C transmission line is allowed.

As intimated by Chief Engineer S&O Wing Jammu, the power supply to Kathua, Hiranagar, Samba, Bari Brahmana, Bishnah, Billawar, Mahanpur and adjoining areas including industrial areas shall remain affected on December 27, 2015 from 10 a m to 3 p m.

          The shutdown is subject to fair weather condition.

 