Rajesh gupta
Jammu, Oct 25: On the directions of Rupesh Kumar , JDA Conducts Demolition Drive at Belicherana, Jammu South, Jammu .
The Enforcement Wing of the Jammu Development Authority (JDA) today conducted a demolition drive at Belicherana, Kh. No. 235, Rakh Raipur, Tehsil Jammu South, to remove an ongoing illegal construction raised on JDA land.
Acting upon specific reports and field verification, it was found that unauthorized construction activity was being carried out without any approval or valid title.
The Enforcement team, under the supervision of the Director Land Management, JDA, dismantled the structure to prevent further encroachment and illegal occupation of government property.
The operation was conducted by JDA in a smooth and orderly execution of the demolition process.
The Jammu Development Authority has reiterated its firm commitment to safeguard government land and maintain strict vigilance against any form of encroachment or unauthorized development.
It added that it is once again advised the general public not to indulge in or facilitate any illegal occupation or transaction of JDA
But strange to mention here that there are some proved questions of "PLAYING DELAY TACTICE" by Revenue Wing of JDA & proved cases of intentional delays in public works because in one case despite two clear reports of encroachment of land of innocent woman by JDA, in which previously cleared by Commission constituted by DC Samba including Revenue officers of JDA stands clearly mentioned that the excess land of 16 marla land may be in demarcation of JDA.
Thereafter then VC categorically directed DLM to vacate the spot in 2018 but despite that Revenue Wing overruled DC Samba & directions of then VC raised some questions on working of concerned Revenue officers needed to be acted upon.
Thereafter, in 2025 again DC Samba submitted report along with latest report, which reads with latest Jamabandhi & Girdawari report & facts submitted by concerned Tehsildar & forwarded by DC Samba with recommendations & Div Com Jammu to VC JDA but so called competent team of Revenue Officers, which is notorious in playing delay tactics in even simple issue the team of incompetent officers of Revenue wing of JDA says that recommendations of DC & Div Com is saying "It may in demarcation is not satisfactory" it should have clearly mentioned in their report that "It is in demarcation of JDA", however VC JDA openly countered the statement of o Revenue Officers in presence of husband of lady that one should understand the meanings of "It may" as no one will write "It is".
However VC has openly directed the Revenue Officers of JDA to put up file with draft on Monday at 12 PM.
Let us see what the so called team of competent, Revenue Wing writes, which shall follow in next edition?
land.
|