DDC Kulgam Reviews Status Of Health Sector Work Projects: Sets Timeline For Completion Of Several Projects

KULGAM, APRIL 06: District Development Commissioner Kulgam, Dr. Bilal-Mohi-Ud-Din-Bhat today chaired a meeting of officers to review the pace and progress of work projects of the health sector in the district.

It was given out that 13 work projects of the health sector have been taken up under languishing projects and the estimate cost of these projects is Rs 25.03 crore.

The DDC directed the concerned to complete 10 languishing work projects by the end of October, 2021. Moreover, it was informed that out of 37 work projects of health sector 4 stands completed and the total estimate cost of these 37 work projects is Rs 146.48 crore.

Under District Capex, 8 work projects have been taken up and 1 stands completed while 7 works are under progress.

Similarly, under PMDP, 5 work projects with an estimate cost of Rs 90.73 crore were taken up and 2 stands completed. Under state Capex 7 projects are coming up with an estimate cost of Rs 13.55 crore.

The DDC directed the officers to work in coordination and added zeal to ensure early completion of all projects of the health sector across the district.

 

Comments

Cross Town News is the no. 1 Weekly Newspaper and Online News Portal in J&K in term of serious News. The rugged Newspaper & Portal is with a substantial difference to read and presence to feel. This newspaper has a vision to deliver the real side of truth to the public . Since it’s inception in 2013 March, It has become No. 1 News medium for people of J&K. Cross Town News has a mission to deliver high quality news across the nation within fraction of time.