DDC Pulwama directs for time bound completion of TLI Scheme


Cinosural International An Elementry School Jammu

 

PULWAMA, JUNE 25: District Development Commissioner Pulwama, Dr. Raghav Langer today issued a realistic timeline for completion of   pending stages of Tral Lift Irrigation (TLI) scheme.

He directed the concerned officers to achieve the targets in a time bound manner so that the project is made fully operational by the end of September 2020.

The DDC said that the 3 remaining pumps of Stage III shall be completed by June 30, 2020 whereas the allied accessories of Stage III shall be delivered by June 30, 2020 so that   all the 4 pumps shall be commissioned by 20 July 2020.

As far as rising mains is concerned, it was also directed that the 2nd line of Stage III shall be completed by June 24, 2020, and shall be commissioned by July 20, 2020 after testing.

In the Stage III, remaining 495 mts of the rising mains shall be completed by 20 July 2020 and hence shall be commissioned by July 30, 2020 after testing.

It was also added that the electric substations shall be completed by July 20, 2020.

Regarding the canal network, in the Stage III, In-progress 2.634 km shall be completed by August 20, 2020 and the remaining 2.651 km shall be completed by 30 September 2020, subject to early settlement of land compensation.

DDC directed the Collector Land Acquisition, Irrigation and Flood Control to settle the disbursement of payment issue at an earliest and   ADC Tral was also directed to resolve land compensation issue without any fail.

The DDC during the visit was accompanied by ADC Tral, Ex. Er. Irrigation and Flood Control, Tehsildar Tral and other concerned.

 