Srinagar, October 09: Govt issued orders for Constitution of Empowered Committee for implementation of the Rehabilitation and Resettlement (R&R) Plan for the project affected families of Keeru and Kwar Hydro Electric Power Projects District Kishtwar J&K in order Dated: 9 .10.2017, copy of which is with Cross Town News, which reads as under:-
In amplification of Government Order No.1088-GAD of 2017 dated 24.08.2017, it is hereby ordered that the Empowered Committee constituted for the implementation of the Rehabilitation and Resettlement (R&R) Plan for the project affected families of Keeru Hydro Electric project (624 MW),
District Kishtwar, shall also finalize and monitor the implementation of Rehabilitation and Resettlement (R&R) Plan for the Project affected families of Kwar Hydro Electric Project (540 MW), District Kishtwar.
|